2022 Bond Issue & Levy Transfer

On April 5, 2022, you — Ozark voters — approved a $19 million no tax increase bond issue. Your vote made a difference and will make our schools safer while accommodating growth. The support of our community is one of our greatest assets.

Since April, we have been busy wrapping up our June 2020 bond projects while kicking off these new bond projects. Here are some highlights:

  • Projects include storm shelters at Tiger Paw Early Childhood Center, Ozark Middle School and Ozark High School, as well as a new entrance at OMS and an indoor activities center at OHS  
  • In September 2022, the Board of Education selected Branco Enterprises Inc. as the construction manager at risk for all projects
  • Construction started spring 2023
  • Estimate completion date on all projects is August 2024 

Project Details 


 

Bond Updates


 

Project Update- Sept. 2023

A lot of work happened at OMS, Tiger Paw and OHS over the summer! The precast storm shelter at OMS was installed and crews are now working to finish the roof. At Tiger Paw Early Childhood Center, moved dirt and erected the storm shelter three months ahead of schedule. At the high school, crews have been moving dirt for the storm shelter as well as an indoor activities center. 

 Ozark Breaks Ground on OHS, Tiger Paw Storm Shelters

Safety and growth took center stage Friday, April 21 as Ozark School District officially broke ground on projects at Ozark High School and Tiger Paw Early Childhood Center. These projects include storm shelters at both locations, as well as an indoor practice facility at OHS, all part of the $19 million no-tax-increase bond issue voters approved on the April 5, 2022, ballot.

Ozark Breaks Ground on OMS Storm Shelter

It might not have been the typical groundbreaking with shovels moving dirt in the sunshine, but the rain didn’t damper the excitement as Ozark School District officially broke ground March 23 on the Ozark Middle School storm shelter and new entrance, a project part of the $19 million no-tax-increase bond issue voters approved on the April 5, 2022, ballot.

Project Update - March 8, 2023

After a year of planning following April 2022 voter approval for a bond to build 3 storm shelters and an indoor practice facility, we are excited to officially start the construction projects and break ground!

  • OMS Groundbreaking will be at 5 p.m. March 23
  • Tiger Paw Groundbreaking will be at 1:45 p.m. March 31
  • Ozark High School Groundbreaking will be at 2:30 p.m. March 31

The public is invited to attend all of the events! We hope to see you there!

Project Update - Dec. 14, 2022

Since April, we have been busy wrapping up our June 2020 bond projects (see details below) while kicking off these new bond projects. Here are some highlights:

  • In September, the Board of Education selected Branco Enterprises Inc. as the construction manager at risk for all four projects, which include storm shelters at Tiger Paw Early Childhood Center, Ozark Middle School and Ozark High School, as well as an indoor activities building at OHS
  • The Design Phase is nearly complete for all projects
  • All projects will go out to bid this winter (2022/23)
  • Estimate completion date on all projects is August 2024